Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:538.2
Total Flight Time:
Start/Last Date:May 09, 2020 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=S-21

Home or Last Project Picture

Mar 07, 2023     Cooling baffles inlet ramp support angles. - (4 hours)       Category: Engine
Continued to work on making reinforcement angles for the inlet ramp areas of the cooling baffles. First one at opening can go under the ramp to promote smooth airflow but as you go back and around the corner you need to go inside of the inlet openings.


 